The work includes the furnishing of the labor, materials and equipment and the construction of the following: Replacement of the existing metal package plants (three separate trains) and metal aerobic digesters with a new membrane bioreactor system (two trains) and two aerobic digesters; new coarse screen building, new fine screen building, new ultraviolet disinfection system, new non-potable water system, miscellaneous manhole and tankage modifications; appurtenant piping, site work, utilities and facilities. The membrane bioreactor system has been pre-selected.
Owner- Nelson County Service Authority
Architect- CHA Consulting Inc.
New Building SF = 4,405
Original Contract Value- $13,763,563