This project consists of 6.6 miles of roadway widening from a two lane section to a four lane divided highway with extensive traffic control. Also, consisting of two bridges, three box culverts, 266,850 CY excavation and borrow, 190,045 tons of asphalt paving, 60,668 LF storm drainage, 107,970 LF curb and gutter, one railroad crossing and traffic signals.
Highlights
- 6.6 miles of roadway widening
- 266,850 CY Excavation/Borrow
- Two Bridges
- 190,045 Tons of Asphalt
- 60,668 LF Storm Drainage
- 107,970 LF Curb & Gutter
- Railroad Crossing
- Completion: June 2016
- Client: NCDOT