Construction is not what we do…it's who we are.

Highlights

  • 30 MGD PS
  • 38,500 LF Pipe
  • Completion Date: August 31, 2017
  • Client: Charlotte-Water

Construction of a new 30 MGD pump station followed by demolition of the existing Steele Creek PS and demolition of the existing Westhall PS.  Project also includes installation of approximately 38,500 lf of underground piping ranging in size from 8” to 60”. Rehabilitation of approximately 2,700 lf of 54” existing sewer and bypass pumping is also required.